No, dates for a process activity cannot be changed from the Platform Client. The Platform client does not have a means to manipulate the dates. It just displays the dates that the system has calculated.
To adjust dates for a process, you must use the Web interface and follow these steps:
- Log in with the Web client
- Make sure that your persona is either Manager or Executive
- Select the opportunity that you wish to change (note you must own the opportunity to modify the dates)
- Select the “Summary” tab on the opportunity
- Select the subtab labeled “Manage”
- On the “Manage Opportunity/Proposal” page, select the “Schedule” button
- Adjust the dates as needed